Work Profile Report [17W319]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 2120/।।।(2)/22-49(प्रा0आ0)/2018
TS Amount (lakhs) : 3298.4 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3298.40
Resanction Cost :
3298.40
Tentative Cost :
3298.40
Exp. Upto Last Fy :
3,157.41
For CFY 2025-2026
Remaining :
140.99
Demand :
140.99
Allotment :
19.38
Exp in CFY :
19.38
Total Up to Date Exp :
3,176.80
Construction Started
Sanction on : 3 years 3 months ago
09 Jun 2022
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
96 %
Tentative Completion date on : 2 weeks 6 days from now
30 Sep 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सेतु एवं प्रोटेक्शन का कार्य पूर्ण। नेपाल एवं भारत की ओर पहुॅच मार्ग का निर्माण कार्य प्रगति पर। -- as on 02-Sep-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: