Work Profile Report [15W880]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E No 17964/2022 Lok Nirman Anubhag-2 dehradun dt 20-03-2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
82.09
Resanction Cost :
82.09
Tentative Cost :
82.09
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
81.99
Demand :
80.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
Sanction on : 1 month 4 days ago
20 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 82.09 has been counted as tentative cost increased from to 82.09 . -- as on 22-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: