Work Profile Report [15W863]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E File No. 53524 Lok Nirman Anubhag-2 dt 26-09-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
58.01
Resanction Cost :
58.01
Tentative Cost :
45.00
Saving
13.01
Exp. Upto Last Fy :
42.66
For CFY 2025-2026
Remaining :
15.35
Demand :
15.35
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
42.66
Work completed
Sanction on : 1 year 6 months ago
26 Sep 2023
Physical Progress:
At start of FY 2025-2026 :
90 %
Up to Date :
90 %
Tentative Completion date on : 5 days 2 hours from now
30 Apr 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0सी0 का कार्य माह अप्रैल, 30 2025 तक पूर्ण कर लिया जायेगा। -- as on 07-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: