Work Profile Report [15W861]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E File No. 53127 Lok Nirman Anubhag-2 dt 09-10-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
102.20
Resanction Cost :
102.20
Tentative Cost :
102.20
Exp. Upto Last Fy :
47.83
For CFY 2025-2026
Remaining :
54.37
Demand :
54.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
47.83
Construction Started
Sanction on : 1 year 6 months ago
09 Oct 2023
Physical Progress:
At start of FY 2025-2026 :
75 %
Up to Date :
75 %
Tentative Completion date on : 2 months 5 days from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
4.20 किमी0 के सापेक्ष 3.00 किमी0 में कार्य पूर्ण शेष कार्य प्रगति में है। -- as on 07-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand