Work Profile Report [15W753]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. No 6021 /III(2)/21 -44 (M.L.A.)/2017 T.C. -III dt 14.12.2021
TS Amount (lakhs) : 359.2 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
202.30
Resanction Cost :
202.30
Tentative Cost :
202.30
Exp. Upto Last Fy :
201.32
For CFY 2025-2026
Remaining :
0.98
Demand :
2.19
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
201.32
In Maintenance After Completion
Sanction on : 3 years 5 months ago
14 Nov 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date : 1 year 6 months ago
30 Sep 2023
Physical Linear Components
Remark
कार्य पूर्ण पी0सी0आर0 भेजी जानी है। 3 वर्षीय अनुऱक्षण का कार्य प्रगति में। -- as on 07-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: