Work Profile Report [15W619]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या 895/।।।(2)/19-44 (एम0एल0ए0)/2017 दिनांक 22.02.2019
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
138.80
Resanction Cost :
138.80
Tentative Cost :
138.80
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
138.70
Demand :
20.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
Alignment Approved
Sanction on : 6 years 2 months ago
22 Feb 2019
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
5 %
Tentative Completion date on : 5 years 3 weeks ago
30 Mar 2020
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वनभूमि प्रस्ताव आनलाइन कर दिया गया है। -- as on 07-May-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand