Work Profile Report [15W488]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 1889/।।।(2)/16-44(एम0एल0ए0) /2015 टी0सी0 दिनांक 09/06/2016
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
537.60
Resanction Cost :
537.60
Tentative Cost :
468.40
Saving
69.20
Exp. Upto Last Fy :
125.86
For CFY 2025-2026
Remaining :
411.74
Demand :
20.00
Allotment :
19.30
Exp in CFY :
19.30
Total Up to Date Exp :
145.16
Work completed
Sanction on : 9 years 6 months ago
09 Jun 2016
Physical Progress:
At start of FY 2025-2026 :
25 %
Up to Date :
25 %
Tentative Completion date on : 7 hours 9 minutes ago
15 Dec 2025
Actual Completion Date : 3 years 2 days ago
13 Dec 2022
Physical Linear Components
Remark
मुआवजा वितरण का कार्य प्रगति पर है। -- as on 03-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: