Work Profile Report [130W16]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : MoRTH की फाइल संख्या I/4044369/2023 एवं कंप्यूटर संख्या 226880 दिनांक 15.12.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
9441.99
Resanction Cost :
7327.14
Tentative Cost :
7327.14
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
7,327.14
Demand :
3,000.00
Allotment :
1,017.06
Exp in CFY :
999.83
Total Up to Date Exp :
999.83
Construction Started
Sanction on : 1 year 5 months ago
15 Dec 2023
Physical Progress:
At start of FY 2025-2026 :
21 %
Up to Date :
34 %
Tentative Completion date on : 10 months 3 days from now
13 Apr 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Slope Treatment Work in Progress. -- as on 26-Jan-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: