Work Profile Report [130W11]

strengthening work from km 232.00 to km 274.00 on NH 119(534) under NH(O) 2020-21 in the state of Uttarakhand
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : NH-119/NEW-534/AP/UK/2021

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

299.31

Resanction Cost :

299.31

Tentative Cost :

299.31

Exp. Upto Last Fy :

0.00

For CFY 2025-2026

Remaining :

299.31

Demand :

3,000.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Unstarted Work

Sanction on : 3 years 3 months ago

10 Feb 2022

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

0 %

Tentative Completion date on : 6 months 3 weeks from now

31 Dec 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
42
42
42
-
Jobs
1
11
11
-

Remark

view all

work not started yet due to delay in forest and LA. -- as on 01-Feb-2025

Rating : 0

No Forest Case in The Work

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand