Work Profile Report [12W505]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई-फाईल सं0 48456 लोक निर्माण अनुभाग-2 देहरादून दिनांक 14.09.2023
TS Amount (lakhs) : 101.7 Lacs
Budget Financial Head : अनुरक्षण ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
101.70
Resanction Cost :
101.70
Tentative Cost :
101.70
Exp. Upto Last Fy :
54.05
For CFY 2025-2026
Remaining :
47.65
Demand :
47.65
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
54.05
Construction Started
Sanction on : 1 year 7 months ago
14 Sep 2023
Physical Progress:
At start of FY 2025-2026 :
65 %
Up to Date :
65 %
Tentative Completion date on : 3 weeks 3 days ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Bond formed on 21.01.2025. Work is in progress -- as on 05-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand