Work Profile Report [12W400]
Tenders
Project Activities
Samples
Administrative Approval Detail : शासनादेश सं0 5068/।।।(2)/18-57(एम0एल0ए0)/2017 टी0सी0 लो0नि0-अनु0 2 दिनांक 15.10.2018
TS Amount (lakhs) : 316.67 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
316.67
Resanction Cost :
316.67
Tentative Cost :
228.00
Saving
88.67
Exp. Upto Last Fy :
226.55
For CFY 2025-2026
Remaining :
90.12
Demand :
4.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
226.55
In Maintenance After Completion
Sanction on : 6 years 6 months ago
15 Oct 2018
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 weeks 3 days ago
31 Mar 2025
Actual Completion Date : 1 year 3 weeks ago
31 Mar 2024
Physical Linear Components
Remark
Overall Saving 88.67 has been recorded as expected cost of work reduced from 316.67 to 228 . पी0सी0आर0 पे्रषित। -- as on 09-Jan-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: