Work Profile Report [129W660]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासनादेश ई फाईल सं0-51297, लोक निर्माण अनुभाग-2 दिनांक 28.03.2023
TS Amount (lakhs) : 53.08 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
53.08
Resanction Cost :
53.08
Tentative Cost :
45.00
Saving
8.08
Exp. Upto Last Fy :
53.08
For CFY 2025-2026
Remaining :
0.00
Demand :
0.80
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
53.08
In Maintenance After Completion
Sanction on : 2 years 3 weeks ago
28 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 1 month ago
18 Mar 2024
Actual Completion Date : 1 year 3 months ago
30 Dec 2023
Physical Linear Components
Remark
Overall Saving 8.08 has been recorded as expected cost of work reduced from 53.08 to 45.00 . PCR Sent -- as on 04-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: