Work Profile Report [129W650]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासनादेश ई फाईल सं0-48594, लोक निर्माण अनुभाग-2 दिनांक 14.03.2023
TS Amount (lakhs) : 811.99 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
811.99
Resanction Cost :
811.99
Tentative Cost :
811.99
Exp. Upto Last Fy :
782.42
For CFY 2025-2026
Remaining :
29.57
Demand :
20.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
782.42
Work completed
Sanction on : 2 years 1 month ago
14 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 months 3 weeks ago
31 Dec 2024
Actual Completion Date : 4 weeks 1 day ago
26 Mar 2025
Physical Linear Components
Remark
कार्य पूर्ण, 01/2025 -- as on 07-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand