Work Profile Report [128W281]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : लोक निर्माण विभाग अनुभाग-2 की ई फाईल सं0 35061/04 दिनांक 12.03.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
234.38
Resanction Cost :
234.38
Tentative Cost :
234.38
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
234.28
Demand :
124.30
Allotment :
44.96
Exp in CFY :
44.12
Total Up to Date Exp :
44.22
Construction Started
Sanction on : 9 months 3 days ago
12 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 11 months 1 week from now
26 Nov 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति में। -- as on 16-Sep-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: