Work Profile Report [126W222]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : सयुक्त सचिव, उत्तराखण्ड शासन के ई0पत्रावली संख्या 74934 दि॰ 01.01.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
217.98
Resanction Cost :
217.98
Tentative Cost :
217.98
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
217.88
Demand :
175.00
Allotment :
140.00
Exp in CFY :
25.88
Total Up to Date Exp :
25.98
Construction Started
Sanction on : 5 months 1 week ago
01 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
25 %
Tentative Completion date on : 1 year 2 weeks from now
29 Jun 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अनुबन्ध गठित। कार्य प्रारम्भ। -- as on 20-May-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: