Back

Office :

All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
MDR 1 48.69 11.00 15.94 20 Sep 2025 31 Oct 2025 11.00 11.00 100.00 %
ODR 1 10.57 6.00 4.50 20 Sep 2025 31 Oct 2025 6.00 6.00 100.00 %
2 59.26 17.00 20.44 17.00 17.00 100.00 %
Division Type Div Seg ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Karnprayag MDR 2128 नन्दप्रयाग-घाट घाट सुतोल कनोल मोटर मार्ग [ Ch. 0.000 - 48.690] 48.690 11.000 15.94 20 Sep 31 Oct 11.000 11.00 100 16 Oct 09:28 am Gyanendra Kumar, Assistant Engineer Civil, PD Karnprayag 12
2 PD Karnprayag ODR 2132 सेमा बैराऊ मोटर मार्ग (थिरपाक काण्डई बैरासकुण्ड मोटर मार्ग) [ Ch. 0.000 - 10.570] 10.570 6.000 4.50 20 Sep 31 Oct 6.000 6.00 100 23 Oct 12:35 pm Yogesh Chandra Pant, Assistant Engineer Civil, PD Karnprayag