All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 1 155.10 33.00 70.00 01 Apr 2025 15 Jun 2025 0.42 33.00 7,857.14 %
MDR 1 92.00 26.00 55.00 01 Apr 2025 30 Jun 2025 0.04 9.00 22,500.00 %
2 247.10 59.00 125.00 0.46 42.00 9,130.43 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Lansdown SH 5591 शहीद संदीप सिंह रावत राज्य मार्ग (घटटूगाड सिलोगी गुमखाल लैंसडौन डेरियाखाल रिखणीखाल बीरौंखाल मोटर मार्ग ) [ Ch. 14.500 - 169.600] 155.100 33.000 70.00 01 Apr 15 Jun 0.420 33.00 7857 23 Apr 12:39 pm Amit Kumar Saini, Assistant Engineer Civil, PD Lansdown 1
2 PD Lansdown MDR 4661 सतपुली दुधारखाल धारकोट सिसल्डी मोटर मार्ग [ Ch. 0.000 - 92.000] 92.000 26.000 55.00 01 Apr 30 Jun 0.040 9.00 22500 23 Apr 12:39 pm Amit Kumar Saini, Assistant Engineer Civil, PD Lansdown