All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 3 114.13 41.00 82.00 01 Apr 2025 30 Apr 2025 38.03 21.00 55.22 %
MDR 2 96.08 18.00 36.00 01 Apr 2025 30 Apr 2025 16.70 0.00 0.00 %
5 210.20 59.00 118.00 54.73 21.00 38.37 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 TD Ghansaali SH 5565 उत्तरकाशी घनसाली तिलवाडा राज्य मार्ग [ Ch. 67.125 - 129.250] 62.125 25.000 50.00 01 Apr 30 Apr 23.190 10.00 43 22 Apr 11:20 am Ankit Bhatt, Assistant Engineer Civil, TD Ghansali 19
2 TD Ghansaali SH 5459 कमद धौन्तरी चमियाला बुढाकेदार अंयारखाल राज्य मार्ग [ Ch. 17.800 - 51.800] 34.000 3.000 6.00 01 Apr 30 Apr 2.780 - - 3
3 TD Ghansaali SH 5468 जाखधार घनसाली राज्य मार्ग [ Ch. 0.000 - 18.000] 18.000 13.000 26.00 01 Apr 30 Apr 12.060 11.00 91 23 Apr 13:02 pm Mahak Singh, Assistant Engineer Civil, TD Ghansali 28
4 TD Ghansaali MDR 5659 घनसाली कोटी अखोड़ी हुलानाखाल मुलगढ मोटर मार्ग [ Ch. 0.000 - 65.775] 65.775 12.000 24.00 01 Apr 30 Apr 11.130 - - 5
5 TD Ghansaali MDR 5658 घनसाली घुत्तू मोटर मार्ग [ Ch. 0.000 - 30.300] 30.300 6.000 12.00 01 Apr 30 Apr 5.570 - - 1