Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 1 54.10 14.00 35.00 01 Apr 2025 25 Jun 2025 0.04 0.00 0.00 %
MDR 1 39.60 9.00 22.00 01 Apr 2025 25 Jun 2025 0.03 0.00 0.00 %
ODR 1 11.30 8.00 20.00 01 Apr 2025 25 Jun 2025 0.02 0.00 0.00 %
3 105.00 31.00 77.00 0.09 0.00 0.00 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Uttarkashi SH 5547 सिलक्यारा बनगांव चापड़ा सरोठ राज्य मार्ग [ Ch. 25.000 - 79.100] 54.100 14.000 35.00 01 Apr 25 Jun 0.040 - - 5
2 CD Uttarkashi MDR 5656 धरासू देवीसौड़ मल्ली बैण्ड.से जोगथ मोटर मार्ग। [ Ch. 0.000 - 39.600] 39.600 9.000 22.00 01 Apr 25 Jun 0.030 - - 3
3 CD Uttarkashi ODR 1943 उडखोला जिब्या टण्डोल मोटर मार्ग [ Ch. 0.000 - 11.300] 11.300 8.000 20.00 01 Apr 25 Jun 0.020 - -