All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 1 18.00 7.00 15.00 01 Apr 2025 30 Apr 2025 7.00 9.00 128.57 %
ODR 1 10.00 10.00 15.00 01 Apr 2025 30 Apr 2025 10.00 10.00 100.00 %
MDR 1 12.76 4.00 5.00 01 Apr 2025 30 Apr 2025 4.00 6.00 150.00 %
3 40.76 21.00 35.00 21.00 25.00 119.05 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 PD Bhatwari SH 5562 उत्तरकाशी घनसाली तिलवाडा राज्य मार्ग [ Ch. 0.000 - 18.000] 18.000 7.000 15.00 01 Apr 30 Apr 7.000 9.00 129 17 Apr 16:07 pm Dharamveer Singh, Assistant Engineer Civil, PD Bhatwari 5
2 PD Bhatwari ODR 1915 भटवाड़ी बार्सू मोटर मार्ग [ Ch. 0.000 - 10.000] 10.000 10.000 15.00 01 Apr 30 Apr 10.000 10.00 100 14 May 13:20 pm Anil Kumar, Assistant Engineer Civil, PD Bhatwari
3 PD Bhatwari MDR 5652 तेखला महिडाण्डा मोटर मार्ग [ Ch. 0.000 - 12.760] 12.760 4.000 5.00 01 Apr 30 Apr 4.000 6.00 150 30 Sep 17:07 pm Dharamveer Singh, Assistant Engineer Civil, PD Bhatwari 5