All Length in KM and Amount in Rs. Lacs

Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 1 25.76 10.00 10.00 01 Apr 2025 30 Jun 2025 0.01 2.00 20,000.00 %
MDR 5 49.95 18.00 38.00 01 Apr 2025 30 Jun 2025 0.02 0.60 3,000.00 %
ODR 1 3.60 3.60 5.00 01 Apr 2025 30 Jun 2025 0.00 0.00
7 79.31 31.60 53.00 0.03 2.60 8,666.67 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Kashipur SH 5817 ढकिया गुलाबो पैगा मुकंदपुर राज्य मार्ग [ Ch. 0.000 - 25.755] 25.755 10.000 10.00 01 Apr 30 Jun 0.010 2.00 20000 18 Apr 08:49 am Pravez Alam, Assistant Engineer Civil, CD Kashipur 21
2 CD Kashipur MDR 5697 काशीपुर मुख्य मोटर मार्ग [ Ch. 0.000 - 21.600] 21.600 3.000 6.00 01 Apr 30 Jun 0.000 0.20 - 23 Apr 10:22 am Narendra Singh Rawat, Assistant Engineer Civil, CD Kashipur
3 CD Kashipur MDR 5698 जसपुर धामपुर मोटर मार्ग [ Ch. 0.000 - 6.000] 6.000 2.000 5.00 01 Apr 30 Jun 0.000 - -
4 CD Kashipur MDR 5699 जसपुर ठाकुरद्वारा मोटर मार्ग [ Ch. 0.000 - 5.000] 5.000 5.000 10.00 01 Apr 30 Jun 0.010 - -
5 CD Kashipur MDR 1634 जसपुर अमानगढ पतरामपुर मोटर मार्ग [ Ch. 0.000 - 7.550] 7.550 3.000 7.00 01 Apr 30 Jun 0.000 0.20 - 23 Apr 10:31 am Narendra Singh Rawat, Assistant Engineer Civil, CD Kashipur
6 CD Kashipur MDR 1636 जसपुर पतरामपुर मोटर मार्ग [ Ch. 0.000 - 9.800] 9.800 5.000 10.00 01 Apr 30 Jun 0.010 0.20 2000 24 Apr 10:56 am Shakhabat , Assistant Engineer Civil, CD Kashipur
7 CD Kashipur ODR 1641 बाजपुर खमरिया नरखेडा मार्ग [ Ch. 0.000 - 3.600] 3.600 3.600 5.00 01 Apr 30 Jun 0.000 - -