Road Type Division Segemnt Total Length Target Length Amount Planned Start Date Planned End Date Till Date Target Till Date Progress %
SH 2 84.05 15.80 43.00 01 Apr 2025 30 Jun 2025 0.02 3.50 17,500.00 %
ODR 2 6.66 3.63 3.50 01 Apr 2025 30 Jun 2025 0.00 0.00
4 90.71 19.43 46.50 0.02 3.50 17,500.00 %
Division Type ID Name Total Length Target Length Amount Planned Start Planned End Till Date Target Progress % Progress On Progress By Images
1 CD Ramnagar SH 5544 सरदारनगर बाजपुर केशोंवाला बन्नाखेडा बैलपडाव कोटाबाग कालाढूंगी मोटर मार्ग राज्य मार्ग [ Ch. 40.000 - 79.800] 39.800 8.800 25.00 01 Apr 30 Jun 0.010 3.50 35000 03 Apr 13:16 pm Hari Nandan Mishra, Assistant Engineer Civil, CD Ramnagar 3
2 CD Ramnagar SH 5530 रामनगर भण्डारपानी अमगड़ी बोहराकोट आखूलढूँगा तल्ली सेठी बेतालघाट रतौड़ा भुजान विशालकोट जैना रींची बिल्लेख राज्य मार्ग [ Ch. 0.000 - 44.250] 44.250 7.000 18.00 01 Apr 30 Jun 0.010 - - 4
3 CD Ramnagar ODR 530 रानीखेत रामनगर मार्ग से गर्जिया मंदिर मार्ग [ Ch. 0.000 - 0.875] 0.875 0.850 1.00 01 Apr 30 Jun 0.000 - -
4 CD Ramnagar ODR 533 अमगडी से पाटकोट तक मोटर मार्ग [ Ch. 0.000 - 5.780] 5.780 2.780 2.50 01 Apr 30 Jun 0.000 - -