Work Profile Report [43W748]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0 सं0 1194/111(2)/19-09(एम0एल0ए0)/ 2017 दि0 28.02.2019
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
6.44
Resanction Cost :
6.44
Tentative Cost :
6.44
Exp. Upto Last Fy :
0.40
For CFY 2025-2026
Remaining :
6.04
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.40
Alignment Approved
Sanction on : 6 years 1 month ago
28 Feb 2019
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
20 %
Tentative Completion date on : 6 months 6 days from now
31 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
इस कार्यालय के पत्रांक 1092/23सी दि0 16.04.2025 द्वारा आपत्तियों का निराकरण कर डी0 एफ0ओ0 नई टिहरी को पुनः प्रेषित । -- as on 16-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: