Work Profile Report [12W299]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 2064/।।।(2)/10-35(प्रा0आ0)/2016 दिनांक 04.07.2016
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
13.50
Resanction Cost :
13.50
Tentative Cost :
13.50
Exp. Upto Last Fy :
0.98
For CFY 2025-2026
Remaining :
12.52
Demand :
0.50
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.98
Construction Started
Sanction on : 8 years 9 months ago
04 Jul 2016
Physical Progress:
At start of FY 2025-2026 :
10 %
Up to Date :
10 %
Tentative Completion date on : 3 weeks 3 days ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रस्ताव गठित, राजस्व विभाग एवं वन विभाग के संबधितों के हस्ताक्षर कराये जा रहे है। -- as on 03-Jan-2025
Assets :
© PWD Uttarakhand