धारकोट से जुलेड़ी मोटर मार्ग (ID: 4887) , निर्माण खण्ड दुगड्डा , Pauri

# KM Closed On Tentative Date Opened On Response Time Open Type Informed By Initial cost Restoration Cost Damage Type Location Chainages Remark PiC geo location lat lng
1 7 2025-06-17 07:20:25 2025-06-17 14:20:25 2025-06-17 12:21:19 5 hours 0 mins Opened Hari Singh Negi ,Junior Engineer Technical ,020019335 0.05 0.10 Slip/ Landslide Marg yatayat hetu band hai -
2 7 2025-07-01 07:54:10 2025-07-01 12:54:10 2025-07-01 14:19:15 6 hours 25 mins Opened Anuj Kumar Singh ,AE ,65006251 0.04 0.08 Slip/ Landslide 30.023300000000 78.346600000000
3 7 2025-07-04 08:19:47 2025-07-04 16:19:47 2025-07-05 07:39:58 23 hours 20 mins Opened Anuj Kumar Singh ,AE ,65006251 0.10 0.18 Slip/ Landslide, Retaining Wall Damage 29.946600000000 78.378940000000
4 8 2025-06-17 07:20:25 2025-06-17 14:20:25 2025-06-17 12:21:33 5 hours 1 mins Opened Hari Singh Negi ,Junior Engineer Technical ,020019335 0.05 0.10 Slip/ Landslide Marg yatayat hetu band hai -
5 8 2025-07-01 07:54:10 2025-07-01 12:54:10 2025-07-01 14:18:55 6 hours 24 mins Opened Anuj Kumar Singh ,AE ,65006251 0.04 0.08 Slip/ Landslide -
6 13 2025-06-25 15:33:47 2025-06-25 18:33:47 2025-06-27 16:07:19 2 days 0 hours Opened Anuj Kumar Singh ,AE ,65006251 0.10 5.00 Retaining Wall Damage 30.024862000000 78.348314000000
Total: 0.38 5.54

Current Road KM Closures (as on 06 Jul 2025)

KM Tentative Opening Date Status
Road is open.

is opened for Traffic