KM |
Closed On |
Tentative Date |
Opened On |
Response Time |
Open Type |
Informed By |
Initial cost |
Restoration Cost |
Damage Type |
Location |
Chainages |
Remark |
PiC |
geo location |
lat |
lng |
1 |
2 |
2025-06-28 03:13:33 |
2025-06-28 17:13:00
|
2025-06-29 13:34:01 |
1 days 10 hours |
Opened |
Prashant Rawat ,AE 2024 ,42270213M01485 |
0.20 |
5.00 |
Slip/ Landslide
|
|
|
मार्ग वर्षा के कारण अस्थायी रूप से अवरुद्ध है। |
|
-
|
|
|
2 |
3 |
2025-06-28 03:13:33 |
2025-06-28 17:13:33
|
2025-06-29 13:34:21 |
1 days 10 hours |
Opened |
Prashant Rawat ,AE 2024 ,42270213M01485 |
0.20 |
5.00 |
Slip/ Landslide
|
|
|
|
|
-
|
|
|
3 |
1 |
2025-06-29 09:02:27 |
2025-07-06 11:02:00
|
|
7 days 1 hours |
|
Prashant Rawat ,AE 2024 ,42270213M01485 |
2.00 |
13.00 |
Washout
|
|
|
Nirpani village is currently accessible via the Kuhed–Maithana–Palethi road, as the approach road from the National Highway side has been washed out. |
|
|
30.356039000000 |
79.319934000000 |
Total: |
2.40 |
23.00 |
|
Current Road KM Closures (as on 06 Jul 2025)
KM |
Tentative Opening Date |
Status |
1 |
2025-07-06 11:02:00 |
Closed |
Road is closed at KM 1 (tentative: 2025-07-06 11:02:00).
Proposed to be open up to:
Sun 06 Jul 2025 11:02
(7 hours 2 minutes 42 seconds from now from now)