बिसाटगांव जान्दणू मोटर मार्ग। (ID: 2119) , निर्माण खण्ड बड़कोट , Uttarkashi

# KM Closed On Tentative Date Opened On Response Time Open Type Informed By Initial cost Restoration Cost Damage Type Location Chainages Remark PiC geo location lat lng ID
1 5 2025-07-15 08:04:00 2025-07-15 17:47:00 2025-07-17 18:15:51 2 days 10 hours Opened Mahesh Kumar ,AE (Civil) ,410011279 0.50 3.00 Slip/ Landslide Slip clearnce 30.683729765115 78.087732302167 9673
2 5 2025-08-16 07:41:22 2025-08-16 17:41:22 2025-08-16 15:13:20 7 hours 31 mins Opened Tanuj Kamboj ,EE ,42270213M00021 0.30 1.00 Slip/ Landslide मार्ग खोलने की कार्यवाही की जा रही है। - 22646
3 5 2025-08-17 10:14:04 2025-08-17 16:14:04 2025-08-17 19:42:19 9 hours 28 mins Opened Tanuj Kamboj ,EE ,42270213M00021 0.30 1.00 Slip/ Landslide जे0सी0बी0 कार्यरत। - 23174
4 5 2025-08-30 08:04:31 2025-08-30 15:04:31 7 hours 0 mins Tanuj Kamboj ,EE ,42270213M00021 0.30 1.50 Slip/ Landslide jcb deployed - 29736
5 3 2025-08-06 10:12:20 2025-08-06 13:12:20 2025-08-06 18:29:18 8 hours 16 mins Opened Tanuj Kamboj ,EE ,42270213M00021 0.50 1.00 Slip/ Landslide मार्ग खोलने की कायवाही की जा रही है। - 16638
6 3 2025-08-07 09:15:08 2025-08-07 16:15:08 2025-08-08 06:38:40 21 hours 23 mins Opened Tanuj Kamboj ,EE ,42270213M00021 0.30 0.80 Slip/ Landslide मार्ग खोलने की कार्यवाही की जा रही है। - 17700
7 3 2025-08-08 07:28:38 2025-08-08 14:28:38 2025-08-08 19:05:59 11 hours 37 mins Opened Tanuj Kamboj ,EE ,42270213M00021 0.20 0.50 Slip/ Landslide मार्ग खोलने की कार्यवाही गतिमान। - 18258
8 3 2025-08-30 08:03:55 2025-08-30 15:03:55 7 hours 0 mins Tanuj Kamboj ,EE ,42270213M00021 0.30 1.00 Slip/ Landslide jcb deployed - 29735
9 4 2025-08-07 09:16:32 2025-08-07 16:16:32 2025-08-08 06:38:49 21 hours 22 mins Opened Tanuj Kamboj ,EE ,42270213M00021 0.30 0.80 Slip/ Landslide मार्ग खोलने की कार्यवाही की जा रही है। - 17703
10 4 2025-08-08 07:29:14 2025-08-08 15:29:14 2025-08-08 18:56:12 11 hours 26 mins Opened Tanuj Kamboj ,EE ,42270213M00021 0.25 0.60 Slip/ Landslide मार्ग खोलने की कार्यवाही गतिमान। - 18260
Total: 3.25 11.20

Current Road KM Closures (as on 30 Aug 2025)

KM Tentative Opening Date Status
5 2025-08-30 15:04:31 Closed
3 2025-08-30 15:03:55 Closed
Road is closed at KM 5 (tentative: 2025-08-30 15:04:31), 3 (tentative: 2025-08-30 15:03:55).

Proposed to be open up to: Sat 30 Aug 2025 15:04 (2 hours 39 minutes 26 seconds from now from now)