गनियाद्योली-पाली-नदुली मोटर मार्ग के किमी. 3 से मोड़ी तक मोटर मार्ग। (ID: 128) , प्रान्तीय खण्ड रानीखेत , Almora

# KM Closed On Tentative Date Opened On Response Time Open Type Informed By Initial cost Restoration Cost Damage Type Location Chainages Remark PiC geo location lat lng ID
1 2 2025-06-26 09:53:09 2025-06-26 16:53:09 2025-06-26 18:17:43 8 hours 24 mins Opened Ajay Tamta ,AE ,070018101 0.10 0.00 Slip/ Landslide - 2121
2 2 2025-07-07 08:59:19 2025-07-07 14:59:19 2025-07-07 12:57:39 3 hours 58 mins Opened Ajay Tamta ,AE ,070018101 0.10 0.00 Slip/ Landslide - 6964
3 2 2025-08-20 08:53:23 2025-08-20 20:30:00 2025-08-20 20:18:50 11 hours 25 mins Opened Ajay Tamta ,AE ,070018101 0.20 0.00 Slip/ Landslide - 25106
4 2 2025-08-24 08:33:26 2025-08-24 15:33:26 2025-08-24 15:37:02 7 hours 3 mins Opened Ajay Tamta ,AE ,070018101 0.05 0.00 Slip/ Landslide Jcb is working at site - 27033
5 2 2025-08-29 11:52:00 2025-08-29 17:52:00 2025-08-29 16:28:32 4 hours 36 mins Opened GEETIKA KATHAYAT ,JET ,42270313F02056 0.04 0.00 Slip/ Landslide machine deployed - 29447
6 1 2025-06-26 09:53:09 2025-06-26 16:53:09 2025-06-26 18:15:01 8 hours 21 mins Opened Ajay Tamta ,AE ,070018101 0.10 0.00 Slip/ Landslide - 2120
7 1 2025-07-07 08:59:19 2025-07-07 14:59:19 2025-07-07 12:57:21 3 hours 58 mins Opened Ajay Tamta ,AE ,070018101 0.10 0.00 Slip/ Landslide - 6963
8 1 2025-08-01 09:36:34 2025-08-01 11:36:00 2025-08-01 17:16:01 7 hours 39 mins Opened Ajay Tamta ,AE ,070018101 0.10 0.00 Slip/ Landslide Jcb deployed. - 14257
9 1 2025-08-15 09:16:30 2025-08-15 12:16:00 2025-08-15 12:19:12 3 hours 2 mins Opened Ajay Tamta ,AE ,070018101 0.04 0.00 Slip/ Landslide Jcb deployed. - 22354
10 1 2025-08-29 11:52:00 2025-08-29 17:52:00 2025-08-29 16:28:25 4 hours 36 mins Opened GEETIKA KATHAYAT ,JET ,42270313F02056 0.04 0.00 Slip/ Landslide machine deployed - 29446
11 3 2025-07-09 09:03:24 2025-07-09 14:03:24 2025-07-09 13:30:53 4 hours 27 mins Opened Ajay Tamta ,AE ,070018101 0.10 0.00 Slip/ Landslide - 7696
12 3 2025-08-24 08:33:26 2025-08-24 15:33:26 2025-08-24 15:37:22 7 hours 3 mins Opened Ajay Tamta ,AE ,070018101 0.05 0.00 Slip/ Landslide Jcb is working at site - 27034
13 4 2025-07-09 09:03:24 2025-07-09 14:03:24 2025-07-09 13:31:03 4 hours 27 mins Opened Ajay Tamta ,AE ,070018101 0.10 0.00 Slip/ Landslide - 7697
14 4 2025-07-15 15:05:12 2025-07-15 17:05:12 2025-07-15 17:29:27 2 hours 24 mins Opened Ajay Tamta ,AE ,070018101 0.06 0.00 Slip/ Landslide Jcb deployed. - 9737
15 4 2025-07-25 09:08:23 2025-07-25 17:08:00 2025-07-25 16:16:50 7 hours 8 mins Opened Ajay Tamta ,AE ,070018101 0.10 0.00 Slip/ Landslide Jcb deployed - 12519
16 4 2025-08-17 08:46:16 2025-08-17 13:46:00 2025-08-17 12:34:33 3 hours 48 mins Opened Ajay Tamta ,AE ,070018101 0.06 0.00 Slip/ Landslide Jcb moved to site - 22989
17 5 2025-07-09 09:03:24 2025-07-09 14:03:24 2025-07-09 13:31:15 4 hours 27 mins Opened Ajay Tamta ,AE ,070018101 0.10 0.00 Slip/ Landslide - 7698
18 5 2025-07-11 10:30:45 2025-07-11 19:00:00 2025-07-11 19:25:56 8 hours 55 mins Opened Ajay Tamta ,AE ,070018101 0.15 0.00 Slip/ Landslide Jcb deployed. - 8614
19 5 2025-07-25 09:08:23 2025-07-25 17:08:00 2025-07-25 16:17:12 7 hours 8 mins Opened Ajay Tamta ,AE ,070018101 0.10 0.00 Slip/ Landslide Jcb deployed - 12520
20 5 2025-08-17 08:46:16 2025-08-17 13:46:00 2025-08-17 12:34:49 3 hours 48 mins Opened Ajay Tamta ,AE ,070018101 0.06 0.00 Slip/ Landslide Jcb moved to site - 22990
21 5 2025-08-26 08:44:50 2025-08-26 15:44:00 2025-08-26 15:34:21 6 hours 49 mins Opened Ajay Tamta ,AE ,070018101 0.12 0.00 Slip/ Landslide Jcb is working at site - 27943
Total: 1.87 0.00

Current Road KM Closures (as on 30 Aug 2025)

KM Tentative Opening Date Status
Road is open.

is opened for Traffic