पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

Balance Cost at Start of Fy : 349.93 Lacs.

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2025 0 0
May, 2025 0 0
Jun, 2025 3 0
Jul, 2025 6.5 0
Aug, 2025 10 0
Sep, 2025 14.25 0
Oct, 2025 20.54 0
Nov, 2025 27.54 0
Dec, 2025 38.01 0
Jan, 2026 52.69 0
Feb, 2026 52.69 0
Mar, 2026 52.69 0

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2025 0 9.64 0
May, 2025 0 24.1 0
Jun, 2025 3 38.56 0
Jul, 2025 6.5 43.38 0
Aug, 2025 10 48.2 0
Sep, 2025 14.25 57.84 0
Oct, 2025 20.54 67.48 0
Nov, 2025 27.54 77.12 0
Dec, 2025 38.01 81.94 0
Jan, 2026 52.69 86.76 0
Feb, 2026 52.69 96.43 0
Mar, 2026 52.69 96.43 0

Instant Demand

Cummulative Demand
Up to Jun-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

3.00 Lacs

History (in Reverse Order)

28 May 2025 3.00
30 Apr 2025 2.00
01 Apr 2025 0.00

IFMS Payments