पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

Balance Cost at Start of Fy : 51.62 Lacs.

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2025 0 0
May, 2025 0 0
Jun, 2025 0 0
Jul, 2025 0 0
Aug, 2025 0 0
Sep, 2025 0 0
Oct, 2025 0 0
Nov, 2025 0 0
Dec, 2025 0 0
Jan, 2026 0 0
Feb, 2026 0 0
Mar, 2026 0 0

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2025 0 4.1 0
May, 2025 10.25 10.25 0
Jun, 2025 16.4 16.4 0
Jul, 2025 18.45 18.45 0
Aug, 2025 20.5 20.5 0
Sep, 2025 24.6 24.6 0
Oct, 2025 28.7 28.7 0
Nov, 2025 32.8 32.8 0
Dec, 2025 34.85 34.85 0
Jan, 2026 36.9 36.9 0
Feb, 2026 41 41 0
Mar, 2026 41 41 0

Instant Demand

Cummulative Demand
Up to Jun-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

16.40 Lacs

History (in Reverse Order)

28 May 2025 16.40
30 Apr 2025 14.00
01 Apr 2025 0.00