पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

Balance Cost at Start of Fy : 383.02 Lacs. New Works Sanctioned in This Fy: 1 No of Rs 111.24 Lacs

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2025 0 0
May, 2025 0 0
Jun, 2025 0 0
Jul, 2025 0 0
Aug, 2025 5 0
Sep, 2025 10 0
Oct, 2025 10 0
Nov, 2025 15 0
Dec, 2025 20 0
Jan, 2026 20 0
Feb, 2026 20 0
Mar, 2026 20 0

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2025 0 0 0
May, 2025 0 0 0
Jun, 2025 0 6 0
Jul, 2025 0 7.5 0
Aug, 2025 0 9 0
Sep, 2025 0 13.5 0
Oct, 2025 0 18 0
Nov, 2025 0 22.5 0
Dec, 2025 0 25.5 0
Jan, 2026 0 27 0
Feb, 2026 0 30 0
Mar, 2026 0 30 0

Instant Demand

Cummulative Demand
Up to Jun-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00