पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर
All amounts in ₹ Lacs
Balance Cost at Start of FY
Works
Sanctioned
Spent
No Savings
Resultant Spillover Amount
As Planned in Works
Month | Target | Achivement |
---|---|---|
Apr, 2025 | 14 | 0 |
May, 2025 | 41.3 | 23.2 |
Jun, 2025 | 51.3 | 23.2 |
Jul, 2025 | 62.5 | 28.63 |
Aug, 2025 | 65 | 28.63 |
Sep, 2025 | 65 | 28.63 |
Oct, 2025 | 115 | 28.63 |
Nov, 2025 | 165 | 28.63 |
Dec, 2025 | 235 | 28.63 |
Jan, 2026 | 315 | 28.63 |
Feb, 2026 | 405 | 28.63 |
Mar, 2026 | 405 | 28.63 |
Financial Target/ Achivement
Month |
Annual Demand |
Target By HQ |
Achivement |
---|---|---|---|
Apr, 2025 | 14 | 6.5 | 0 |
May, 2025 | 41.3 | 16.25 | 23.2 |
Jun, 2025 | 51.3 | 26 | 23.43 |
Jul, 2025 | 62.5 | 29.25 | 34.92 |
Aug, 2025 | 65 | 32.5 | 34.92 |
Sep, 2025 | 65 | 39 | 34.92 |
Oct, 2025 | 65 | 45.5 | 34.92 |
Nov, 2025 | 65 | 52 | 34.92 |
Dec, 2025 | 65 | 55.25 | 34.92 |
Jan, 2026 | 65 | 58.5 | 34.92 |
Feb, 2026 | 65 | 65 | 34.92 |
Mar, 2026 | 65 | 65 | 34.92 |
Instant Demand
Cummulative Demand
Up to Aug-2025
0 Lacs
History (in Reverse Order)
Allotment
Cummulative Allotment
51.30 Lacs
History (in Reverse Order)
IFMS Payments