पुलो का निर्माण एंव सुद्ढीकरण कार्य-राज्य सैक्टर

Financial Analysis

All amounts in ₹ Lacs

Starting Balance

794.88

Balance Cost at Start of FY

New Works

2

Works

729.55

Sanctioned

0.00

Spent

Savings

0.00

No Savings

Final Spillover Calculation

794.88 + 729.55 = 1,524.43

Resultant Spillover Amount

As Planned in Works

Month Target Achivement
Apr, 2025 14 0
May, 2025 41.3 23.2
Jun, 2025 51.3 23.2
Jul, 2025 62.5 28.63
Aug, 2025 65 28.63
Sep, 2025 65 28.63
Oct, 2025 115 28.63
Nov, 2025 165 28.63
Dec, 2025 235 28.63
Jan, 2026 315 28.63
Feb, 2026 405 28.63
Mar, 2026 405 28.63

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2025 14 6.5 0
May, 2025 41.3 16.25 23.2
Jun, 2025 51.3 26 23.43
Jul, 2025 62.5 29.25 34.92
Aug, 2025 65 32.5 34.92
Sep, 2025 65 39 34.92
Oct, 2025 65 45.5 34.92
Nov, 2025 65 52 34.92
Dec, 2025 65 55.25 34.92
Jan, 2026 65 58.5 34.92
Feb, 2026 65 65 34.92
Mar, 2026 65 65 34.92

Instant Demand

Cummulative Demand
Up to Aug-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

51.30 Lacs

History (in Reverse Order)

15 Jul 2025 51.30
03 Jul 2025 51.30
28 May 2025 51.30
30 Apr 2025 51.30
01 Apr 2025 0.00

IFMS Payments

2025-05-19 10.30
2025-05-26 23.20
2025-07-10 23.43
2025-07-28 28.63