चालू निर्माण कार्य-राज्य सैक्टर

Balance Cost at Start of Fy : 6111.34 Lacs.

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2025 0 0
May, 2025 488.79 0
Jun, 2025 977.57 0
Jul, 2025 1299.83 0
Aug, 2025 1622.09 0
Sep, 2025 1954.04 0
Oct, 2025 2439.76 0
Nov, 2025 2925.48 0
Dec, 2025 3425.94 0
Jan, 2026 3844.08 0
Feb, 2026 4262.19 0
Mar, 2026 4262.19 0

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2025 0 0 0
May, 2025 488.79 0 0
Jun, 2025 977.57 0 0
Jul, 2025 1299.83 0 0
Aug, 2025 1622.09 0 0
Sep, 2025 1954.04 0 0
Oct, 2025 2439.76 0 0
Nov, 2025 2925.48 0 0
Dec, 2025 3425.94 0 0
Jan, 2026 3844.08 0 0
Feb, 2026 4262.19 0 0
Mar, 2026 4262.19 0 0

Instant Demand

Cummulative Demand
Up to Apr-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

IFMS Payments