चालू निर्माण कार्य-राज्य सैक्टर

Balance Cost at Start of Fy : 4362.69 Lacs.

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2025 0 0
May, 2025 99.11 0
Jun, 2025 295.12 0
Jul, 2025 343.12 0
Aug, 2025 381.49 0
Sep, 2025 503.58 0
Oct, 2025 644.21 0
Nov, 2025 686.27 0
Dec, 2025 818.56 0
Jan, 2026 837.04 0
Feb, 2026 974.11 0
Mar, 2026 974.11 0

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2025 0 0 0
May, 2025 87 0 0
Jun, 2025 259 0 0
Jul, 2025 329 0 0
Aug, 2025 384 0 0
Sep, 2025 429 0 0
Oct, 2025 584 0 0
Nov, 2025 754 0 0
Dec, 2025 799 0 0
Jan, 2026 819 0 0
Feb, 2026 849 0 0
Mar, 2026 849 0 0

Instant Demand

Cummulative Demand
Up to Apr-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

IFMS Payments