सड़क सुरक्षा कार्य

Balance Cost at Start of Fy : 1707.50 Lacs.

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2025 0 0
May, 2025 300 357.06
Jun, 2025 630 357.06
Jul, 2025 874.99 357.06
Aug, 2025 1070.62 357.06
Sep, 2025 1177.51 357.06
Oct, 2025 1241.72 357.06
Nov, 2025 1241.72 357.06
Dec, 2025 1241.72 357.06
Jan, 2026 1241.72 357.06
Feb, 2026 1241.72 357.06
Mar, 2026 1241.72 357.06

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2025 0 0 0
May, 2025 300 0 0
Jun, 2025 630 0 0
Jul, 2025 874.99 0 0
Aug, 2025 1070.62 0 0
Sep, 2025 1177.51 0 0
Oct, 2025 1234.02 0 0
Nov, 2025 1234.02 0 0
Dec, 2025 1234.02 0 0
Jan, 2026 1234.02 0 0
Feb, 2026 1234.02 0 0
Mar, 2026 1234.02 0 0

Instant Demand

Cummulative Demand
Up to Jun-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

480.00 Lacs

History (in Reverse Order)

02 May 2025 480.00
01 Apr 2025 0.00

IFMS Payments

2025-05-23 0.12
2025-05-27 90.74
2025-05-30 356.81
2025-05-31 357.06