सड़क सुरक्षा कार्य

Balance Cost at Start of Fy : 2239.47 Lacs.

All Amount in Rs. Lacs

As Planned in Works

Month Target Achivement
Apr, 2025 0 947.84
May, 2025 0 1219.54
Jun, 2025 1013.02 1232.74
Jul, 2025 1013.02 1232.74
Aug, 2025 1683.85 1232.74
Sep, 2025 2050.85 1232.74
Oct, 2025 2239.48 1232.74
Nov, 2025 2239.48 1232.74
Dec, 2025 2239.48 1232.74
Jan, 2026 2239.48 1232.74
Feb, 2026 2239.48 1232.74
Mar, 2026 2239.48 1232.74

Financial Target/ Achivement

Month Annual
Demand
Target
By HQ
Achivement
Apr, 2025 0 0 0
May, 2025 0 0 0
Jun, 2025 0 0 0
Jul, 2025 0 0 0
Aug, 2025 0 0 0
Sep, 2025 0 0 0
Oct, 2025 0 0 0
Nov, 2025 0 0 0
Dec, 2025 0 0 0
Jan, 2026 0 0 0
Feb, 2026 0 0 0
Mar, 2026 0 0 0

Instant Demand

Cummulative Demand
Up to Jun-2025

0 Lacs

History (in Reverse Order)

01 Apr 2025 0.00

Allotment

Cummulative Allotment

1250.00 Lacs

History (in Reverse Order)

02 May 2025 1,250.00
01 Apr 2025 0.00

IFMS Payments

2025-04-30 947.85
2025-05-07 948.01
2025-05-19 948.16
2025-05-20 1,219.74
2025-05-30 1,219.80
2025-06-03 1,299.85
2025-06-06 1,316.26