5707 - NH Srinagar - Tehri
Total Damage Spots
Total Estimated Cost
Completed
Pending
EE Office: NH Srinagar
District: Tehri
Segment ID: 1, EE Segment ID: 5707
Pics Count: 20
30-06-2025
Reconstruction of Retaining Wall. The construction of the retaining wall includes the following provisions:
Remark: Estimate Prepared.
30-06-2025
Reconstruction of Retaining Wall. The construction of the retaining wall includes the following provisions:
Remark: Estimate Prepared.
30-06-2025
Reconstruction of Wall is required. Retaining wall work includes the following provisions:
Remark: Estimate Prepared.
05-07-2025
Construction of Retaining Wall. The construction of the retaining wall includes the following provisions:
Remark: Estimate Prepared.
17-07-2025
Slope Protection work required and protection work includes the following provisions:
Remark: Estimate Prepared.
20-07-2025
Reconstruction of Retaining Wall. The construction of the retaining wall includes the following provisions:
Remark: Estimate Prepared.
23-07-2025
Reconstruction of Retaining wall is required. Retaining wall work includes the following provisions:
Remark: Estimate Prepared.
23-07-2025
Extra hill side cutting of road is required. Extra hill side cutting work includes the following provisions:
Remark: Estimate Prepared.
25-07-2025
Reconstruction of Retaining wall is required. Retaining wall work includes the following provisions:
Remark: Estimate Prepared.
06-08-2025
Construction of Retaining Wall. The construction of the retaining wall includes the following provisions:
Remark: Estimate Prepared.
06-08-2025
Construction of Retaining Wall. The construction of the retaining wall includes the following provisions:
Remark: Estimate Prepared.
06-08-2025
Slope treatment work required.
Remark: Estimate to be prepared by THDC
07-08-2025
Reconstruction of Retaining Wall. The construction of the retaining wall includes the following provisions:
Remark: Estimate Prepared.
07-08-2025
Construction of Retaining Wall. The construction of the retaining wall includes the following provisions:
Remark: Estimate Prepared.
07-08-2025
Protection of foundation ofwall is required.
Remark: Estimate Prepared.
12-08-2025
Reconstruction of Retaining Wall. The construction of the retaining wall includes the following provisions:
Remark: Estimate Prepared.
12-08-2025
Reconstruction of Retaining Wall. The construction of the retaining wall includes the following provisions:
Remark: Estimate Prepared.
12-08-2025
Reconstruction of Wall is required.
Remark: Estimate is prapared.
19-08-2025
Reconstruction of Retaining wall is required. Retaining wall work includes the following provisions:
Remark: Estimate Prepared.
20-08-2025
Reconstruction of retaining wall and sureface courses work is required. Retaining work includes the following provisions:
Remark: Estimate Prepared.
ID | Date | Location | Cost (₹) | Status | Yojana |
---|---|---|---|---|---|
33 | 30-06-2025 | Shivpuri | 4.81 | Estimation Done | Not Decided |
34 | 30-06-2025 | Shivpuri | 0.89 | Estimation Done | Not Decided |
53 | 30-06-2025 | Kaliyasaur | 34.69 | Estimation Done | Not Decided |
43 | 05-07-2025 | Shivmurti | 11.15 | Estimation Done | Not Decided |
45 | 17-07-2025 | Devprayag | 1.52 | Estimation Done | Not Decided |
41 | 20-07-2025 | Bachelikhal | 1.51 | Estimation Done | Not Decided |
49 | 23-07-2025 | Mulyagaon | 32.19 | Estimation Done | Not Decided |
50 | 23-07-2025 | Mulyagaon | 33.15 | Estimation Done | Not Decided |
46 | 25-07-2025 | Devprayag | 9.83 | Estimation Done | Not Decided |
39 | 06-08-2025 | Kaudiyala | 15.24 | Estimation Done | Not Decided |
36 | 06-08-2025 | Kaudiyala | 20.62 | Estimation Done | Not Decided |
183 | 06-08-2025 | Farshu | 65.00 | Identified | Not Decided |
42 | 07-08-2025 | Teendhara | 1.62 | Estimation Done | Not Decided |
37 | 07-08-2025 | Kaudiyala | 4.70 | Estimation Done | Not Decided |
67 | 07-08-2025 | Singtali | 25.56 | Estimation Done | Not Decided |
38 | 12-08-2025 | Kaudiyala | 16.52 | Estimation Done | Not Decided |
32 | 12-08-2025 | Shivpuri | 41.98 | Estimation Done | Not Decided |
52 | 12-08-2025 | Ufalda | 11.39 | Estimation Done | Not Decided |
47 | 19-08-2025 | Devprayag | 52.33 | Estimation Done | Not Decided |
51 | 20-08-2025 | Jiyalgarh | 47.88 | Estimation Done | Not Decided |
Try adjusting your filters to see more results