[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
192.550 - 192.580
|
30.000 |
29.9472000000, 78.6892900000 |
Estimation Done |
8 |
2025-04-01 00:00:00 |
|
|
installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
192.775 - 192.863
|
88.000 |
29.9491200000, 78.6884000000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
193.225 - 193.261
|
36.000 |
29.9490200000, 78.6914000000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
193.800 - 193.824
|
24.000 |
29.9489900000, 78.6927800000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
193.875 - 193.907
|
32.000 |
29.9494100000, 78.6922900000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
195.950 - 196.018
|
68.000 |
29.9639700000, 78.6857600000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
196.250 - 196.314
|
64.000 |
29.9632800000, 78.6857600000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
196.425 - 196.525
|
100.000 |
29.9617600000, 78.6887500000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
196.650 - 196.738
|
88.000 |
29.9605000000, 78.6895100000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
196.800 - 196.916
|
116.000 |
29.9589900000, 78.6904400000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
197.325 - 197.429
|
104.000 |
29.9565300000, 78.6916600000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
197.600 - 197.724
|
124.000 |
29.9541800000, 78.6926000000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
197.850 - 197.922
|
72.000 |
29.9528200000, 78.6931400000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
198.075 - 198.125
|
50.000 |
29.9520000000, 78.6945400000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
198.175 - 198.219
|
44.000 |
29.9508200000, 78.6953900000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
198.300 - 198.444
|
144.000 |
29.9520300000, 78.6950500000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
198.750 - 198.806
|
56.000 |
29.9549300000, 78.6936100000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
198.975 - 199.039
|
64.000 |
29.9568000000, 78.6932700000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
199.150 - 199.210
|
60.000 |
29.9578900000, 78.6938100000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
199.350 - 199.414
|
64.000 |
29.9563100000, 78.6939500000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
199.425 - 199.511
|
86.000 |
29.9552300000, 78.6942100000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
199.650 - 199.726
|
76.000 |
29.9543000000, 78.6954100000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
200.000 - 200.054
|
54.000 |
29.9552600000, 78.6947600000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
200.525 - 200.609
|
84.000 |
29.9597100000, 78.6957900000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
201.025 - 201.097
|
72.000 |
29.9628100000, 78.6967600000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
201.250 - 201.322
|
72.000 |
29.9645100000, 78.6976400000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
201.400 - 201.508
|
108.000 |
29.9657300000, 78.6962900000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
201.550 - 201.622
|
72.000 |
29.9664900000, 78.6969600000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
201.850 - 201.920
|
70.000 |
29.9650600000, 78.6960600000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
202.550 - 202.614
|
64.000 |
29.9655700000, 78.6946700000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
202.775 - 202.819
|
44.000 |
29.9660700000, 78.6934200000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
203.275 - 203.293
|
18.000 |
29.9686600000, 78.6944200000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
203.575 - 203.600
|
25.000 |
29.9712300000, 78.6949100000 |
Estimation Done |
8 |
|
|
|
installed under road safety |
Jul 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
222.000 - 222.076
|
76.000 |
30.0693110000, 78.7190240000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
223.300 - 223.390
|
90.000 |
30.0709840000, 78.7193990000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
223.600 - 223.640
|
40.000 |
30.0805200000, 78.7184180000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
223.700 - 223.810
|
110.000 |
30.4888000000, 78.4312300000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
225.400 - 225.520
|
120.000 |
30.0887580000, 78.7221590000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
226.000 - 226.040
|
40.000 |
30.5699000000, 78.4397400000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
227.100 - 227.160
|
60.000 |
30.5715000000, 78.4432700000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
227.700 - 227.810
|
110.000 |
30.5802000000, 78.4432700000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
228.300 - 228.404
|
104.000 |
30.5903000000, 78.4455800000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
228.900 - 228.960
|
60.000 |
30.6089000000, 78.4484100000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
229.000 - 229.190
|
190.000 |
30.6158000000, 78.4491000000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
229.600 - 229.648
|
48.000 |
30.1050180000, 78.7511890000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
231.050 - 231.240
|
190.000 |
30.1082120000, 78.7545540000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
233.200 - 233.450
|
250.000 |
30.1204300000, 78.7661030000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
234.000 - 234.048
|
48.000 |
30.1240020000, 78.7711590000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
234.200 - 234.290
|
90.000 |
30.1246480000, 78.7717970000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
234.300 - 234.380
|
80.000 |
30.1254730000, 78.7726900000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
234.450 - 234.478
|
28.000 |
30.1264190000, 78.7713710000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
234.500 - 234.540
|
40.000 |
30.1270830000, 78.7708420000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
234.800 - 234.856
|
56.000 |
30.1264430000, 78.7689920000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[62]
Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway)
|
Crash barrier |
235.100 - 235.210
|
110.000 |
30.1265960000, 78.7679120000 |
Estimation Done |
0 |
|
|
|
Installed under road safety |
Aug 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
0.000 - 0.800
|
800.000 |
30.1209050000, 78.7944330000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
0.800 - 0.860
|
60.000 |
30.1208320000, 78.7938840000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
0.860 - 0.910
|
50.000 |
30.1208080000, 78.7934690000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
0.910 - 0.938
|
28.000 |
30.1207530000, 78.7931940000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
0.938 - 1.308
|
370.000 |
30.1223200000, 78.7901900000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
1.308 - 1.508
|
200.000 |
30.1227900000, 78.7898100000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
1.508 - 1.708
|
200.000 |
30.1237300000, 78.7884400000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
1.708 - 1.764
|
56.000 |
30.1239900000, 78.7879200000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
1.764 - 1.814
|
50.000 |
30.1238900000, 78.7874800000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
1.814 - 1.858
|
44.000 |
30.1241300000, 78.7871400000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
1.858 - 3.108
|
1250.000 |
30.1339100000, 78.7827900000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
3.108 - 3.166
|
58.000 |
30.1341000000, 78.7823300000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
3.166 - 3.206
|
40.000 |
30.1343100000, 78.7822500000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
3.206 - 3.306
|
100.000 |
30.1352100000, 78.7814400000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
3.306 - 3.346
|
40.000 |
30.1352100000, 78.7814100000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
3.346 - 3.450
|
104.000 |
30.1354900000, 78.7808900000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
3.450 - 3.600
|
150.000 |
30.1361200000, 78.7885800000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
3.600 - 3.628
|
28.000 |
30.1362900000, 78.7786000000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
3.628 - 3.828
|
200.000 |
30.1381300000, 78.7777200000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
3.828 - 3.860
|
32.000 |
30.1381600000, 78.7776900000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
3.860 - 3.960
|
100.000 |
30.1398500000, 78.7775700000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
3.960 - 4.010
|
50.000 |
30.1398700000, 78.7777000000 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
4.010 - 4.110
|
100.000 |
30.1399500000, 78.7760900000 |
Identified |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
4.110 - 4.134
|
24.000 |
30.1400800000, 78.7759100000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
4.134 - 4.284
|
150.000 |
30.1412800000, 78.7751900000 |
Identified |
9 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
4.284 - 4.328
|
44.000 |
30.1416700000, 78.7750800000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
4.328 - 4.478
|
150.000 |
30.1427000000, 78.7740600000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
4.478 - 4.608
|
130.000 |
30.1435100000, 78.7736500000 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
4.608 - 4.708
|
100.000 |
30.1430400000, 78.7744200000 |
Estimation Done |
1 |
|
|
|
Residential area , so no need of crash barrier |
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
4.708 - 4.858
|
150.000 |
30.1434100000, 78.7739800000 |
Identified |
9 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
4.858 - 4.906
|
48.000 |
30.1437500000, 78.7736700000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
4.906 - 5.026
|
120.000 |
30.1443100000, 78.7729800000 |
Identified |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
5.026 - 5.076
|
50.000 |
30.1442500000, 78.7724600000 |
Estimation Done |
0 |
|
|
|
Residential area , so no need of crash barrier |
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
5.076 - 5.154
|
78.000 |
30.1447500000, 78.7723200000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
5.154 - 5.254
|
100.000 |
30.1447600000, 78.7723300000 |
Estimation Done |
1 |
|
|
|
Residential area , so no need of crash barrier |
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
5.254 - 5.954
|
700.000 |
30.1512000000, 78.7701000000 |
Estimation Done |
1 |
|
|
|
Residential area , so no need of crash barrier |
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
5.954 - 6.354
|
400.000 |
30.1534400000, 78.7769800000 |
Identified |
9 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
6.354 - 6.394
|
40.000 |
30.1534600000, 78.7668100000 |
Estimation Done |
1 |
|
|
|
Residential area , so no need of crash barrier |
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
6.394 - 6.644
|
250.000 |
30.1542300000, 78.7650600000 |
Identified |
9 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
6.644 - 6.744
|
100.000 |
30.1545500000, 78.7649400000 |
Estimation Done |
0 |
|
|
|
Residential area , no need of crash barrier |
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
6.744 - 6.849
|
105.000 |
30.1549200000, 78.7647200000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
6.849 - 6.899
|
50.000 |
30.1554400000, 78.7641900000 |
Estimation Done |
1 |
|
|
|
Residential area , so no need of crash barrier |
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
6.899 - 7.049
|
150.000 |
30.1557700000, 78.7628200000 |
Treatment in Progress |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
7.049 - 7.499
|
450.000 |
30.1589100000, 78.7616000000 |
Estimation Done |
1 |
|
|
|
Residential area , so no need of crash barrier |
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
7.499 - 7.699
|
200.000 |
30.1603800000, 78.7708900000 |
Identified |
9 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
7.699 - 7.819
|
120.000 |
30.1605900000, 78.7600500000 |
Estimation Done |
1 |
|
|
|
Residential area , so no need of crash barrier |
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
7.819 - 8.819
|
1000.000 |
30.1623200000, 78.7534300000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
8.819 - 9.383
|
564.000 |
30.1591400000, 78.7486300000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
9.383 - 9.563
|
180.000 |
30.1593500000, 78.7474400000 |
Estimation Done |
1 |
|
|
|
Residential area , so no need of crash barrier |
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
9.563 - 10.703
|
1140.000 |
30.1596100000, 78.7474400000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
10.703 - 10.803
|
100.000 |
30.1560200000, 78.7344500000 |
Estimation Done |
1 |
|
|
|
Residential area , so no need of crash barrier |
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
10.803 - 10.903
|
100.000 |
30.1559800000, 78.7332900000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
10.903 - 11.303
|
400.000 |
30.1570600000, 78.7293900000 |
Estimation Done |
1 |
|
|
|
Residential area , so no need of crash barrier |
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
11.303 - 11.603
|
300.000 |
30.1574700000, 78.7288900000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
11.603 - 13.403
|
1800.000 |
30.1680300000, 78.7151800000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
13.403 - 13.453
|
50.000 |
30.1682800000, 78.7149300000 |
Estimation Done |
1 |
|
|
|
Residential area , so no need of crash barrier |
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
13.453 - 13.549
|
96.000 |
30.1694700000, 78.7147100000 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
13.549 - 13.589
|
40.000 |
30.1695400000, 78.7145900000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
13.589 - 14.849
|
1260.000 |
30.1695800000, 78.7146800000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
14.849 - 14.999
|
150.000 |
30.1775700000, 78.7055600000 |
Estimation Done |
1 |
|
|
|
Residential area , so no need of crash barrier |
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
14.999 - 15.503
|
504.000 |
30.1786100000, 78.7004200000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
15.503 - 15.703
|
200.000 |
30.1782600000, 78.6992900000 |
Identified |
9 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
15.703 - 15.843
|
140.000 |
30.1772500000, 78.7001600000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
15.843 - 15.903
|
60.000 |
30.1770200000, 78.6994600000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
15.903 - 16.003
|
100.000 |
30.6175300000, 78.6991100000 |
Estimation Done |
1 |
|
|
|
Residential area , so no need of crash barrier |
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
16.003 - 16.683
|
680.000 |
30.1724100000, 78.6935300000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
16.683 - 16.753
|
70.000 |
30.1719800000, 78.6936800000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
16.753 - 17.117
|
364.000 |
30.1692900000, 78.6938200000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
17.117 - 17.277
|
160.000 |
30.1693100000, 78.6938200000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
17.277 - 17.329
|
52.000 |
30.1684400000, 78.6939500000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
17.329 - 17.479
|
150.000 |
30.1682300000, 78.6939600000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
17.479 - 17.563
|
84.000 |
30.1682600000, 78.6938900000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
17.563 - 17.683
|
120.000 |
30.1671400000, 78.6928700000 |
Estimation Done |
1 |
|
|
|
Residential area , so no need of crash barrier |
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
17.683 - 19.447
|
1764.000 |
30.1566000000, 78.6793700000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
19.447 - 19.647
|
200.000 |
30.1555900000, 78.6770700000 |
Estimation Done |
1 |
|
|
|
Residential area , so no need of crash barrier |
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
19.647 - 19.791
|
144.000 |
30.1558500000, 78.6758600000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
19.791 - 19.951
|
160.000 |
30.1558800000, 78.6758600000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
19.951 - 20.001
|
50.000 |
30.1559200000, 78.6742100000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
20.000 - 20.750
|
750.000 |
30.1556527800, 78.7694833300 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
20.770 - 20.820
|
50.000 |
30.1509777800, 78.6699361100 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
20.840 - 21.170
|
330.000 |
30.1506638900, 78.6698277800 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
21.220 - 21.470
|
250.000 |
30.1488000000, 78.6670888900 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
21.500 - 21.920
|
420.000 |
30.1491333300, 78.6644555600 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
22.000 - 22.660
|
660.000 |
30.1462416700, 78.6649916700 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
22.700 - 23.900
|
1200.000 |
30.1416888900, 78.6667694400 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
23.950 - 24.520
|
570.000 |
30.1383527800, 78.6602666700 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
24.550 - 24.695
|
145.000 |
30.1388805600, 78.6579972200 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
24.700 - 24.950
|
250.000 |
30.1401583300, 78.6563305600 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
24.950 - 25.930
|
980.000 |
30.1399611100, 78.6541500000 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
25.950 - 26.230
|
280.000 |
30.1400138900, 78.6437111100 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
26.250 - 26.300
|
50.000 |
30.1375166700, 78.6432111100 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
26.310 - 26.450
|
140.000 |
30.1369944400, 78.6427944400 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
26.450 - 26.510
|
60.000 |
30.1355583300, 78.6422416700 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
26.705 - 26.775
|
70.000 |
30.1333916700, 78.6422333300 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
26.805 - 26.865
|
60.000 |
30.1327027800, 78.6419250000 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
26.915 - 27.285
|
370.000 |
30.1318500000, 78.6420333300 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
27.305 - 27.335
|
30.000 |
30.1326222200, 78.6384972200 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
27.505 - 27.535
|
30.000 |
30.1328722200, 78.6366277800 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
27.570 - 27.610
|
40.000 |
30.1328444400, 78.6360444400 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
27.920 - 27.970
|
50.000 |
30.1326194400, 78.6327388900 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
28.053 - 28.103
|
50.000 |
30.1319083300, 78.6321305600 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
28.205 - 28.235
|
30.000 |
30.1313972200, 78.6309444400 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
28.235 - 28.405
|
170.000 |
30.1314805600, 78.6306305600 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
28.410 - 28.460
|
50.000 |
30.1315583300, 78.6291500000 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
28.460 - 28.510
|
50.000 |
30.1318250000, 78.6289194400 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
28.510 - 28.570
|
60.000 |
30.1317027800, 78.6284388900 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
28.600 - 29.160
|
560.000 |
30.1311833300, 78.6277916700 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
29.180 - 29.900
|
720.000 |
30.1313583300, 78.6241500000 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
29.900 - 29.930
|
30.000 |
30.1322416700, 78.6206805600 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
29.930 - 30.480
|
550.000 |
30.1319666700, 78.6204444400 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
30.500 - 31.475
|
975.000 |
30.1306666700, 78.6164722200 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
31.520 - 34.235
|
2715.000 |
30.1227527800, 78.6162638900 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
34.270 - 34.390
|
120.000 |
30.1200083300, 78.6305361100 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
34.390 - 34.450
|
60.000 |
30.1181916700, 78.6322527800 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
34.450 - 34.475
|
25.000 |
30.1176250000, 78.6320055600 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
34.495 - 34.541
|
46.000 |
30.1171722200, 78.6323166700 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
34.541 - 34.601
|
60.000 |
30.1168138900, 78.6323666700 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
34.601 - 34.791
|
190.000 |
30.1163222200, 78.6323861100 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
34.825 - 35.143
|
318.000 |
30.1152444400, 78.6339888900 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
35.245 - 35.315
|
70.000 |
30.1126777800, 78.6332527800 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
35.315 - 35.345
|
30.000 |
30.1124972200, 78.6325944400 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
35.345 - 35.395
|
50.000 |
30.1126055600, 78.6324388900 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
35.395 - 35.435
|
40.000 |
30.1129194400, 78.6327083300 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
35.435 - 35.525
|
90.000 |
30.1133138900, 78.6329833300 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
35.525 - 35.755
|
230.000 |
30.1136194400, 78.6333833300 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
35.755 - 35.915
|
160.000 |
30.1157472200, 78.6327361100 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
35.915 - 36.029
|
114.000 |
30.1161611100, 78.6314222200 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
36.030 - 36.070
|
40.000 |
30.1169722200, 78.6313361100 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
36.070 - 36.196
|
126.000 |
30.1173388900, 78.6311333300 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
36.200 - 36.340
|
140.000 |
30.1180833300, 78.6302111100 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
36.355 - 36.380
|
25.000 |
30.1169777800, 78.6302194400 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
36.380 - 36.456
|
76.000 |
30.1167166700, 78.6300694400 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
36.500 - 36.620
|
120.000 |
30.1160972200, 78.6296472200 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
36.620 - 36.665
|
45.000 |
30.1148805600, 78.6292027800 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
36.700 - 36.758
|
58.000 |
30.1146388900, 78.6289722200 |
Estimation Done |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
36.760 - 36.820
|
60.000 |
30.1144000000, 78.6286861100 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
36.820 - 37.040
|
220.000 |
30.1140083300, 78.6281555600 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
37.040 - 37.136
|
96.000 |
30.1130250000, 78.6266194400 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
37.150 - 37.536
|
386.000 |
30.1126222200, 78.6260666700 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
37.540 - 37.574
|
34.000 |
30.1138944400, 78.6239055600 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
37.575 - 37.635
|
60.000 |
30.1140388900, 78.6236611100 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
37.635 - 37.695
|
60.000 |
30.1143694400, 78.6231416700 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
37.695 - 38.359
|
664.000 |
30.1157361100, 78.6234277800 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
38.360 - 38.430
|
70.000 |
30.1181916700, 78.6219138900 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
38.430 - 38.470
|
40.000 |
30.1173027800, 78.6219277800 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
38.470 - 38.510
|
40.000 |
30.1169944400, 78.6217500000 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
38.510 - 39.140
|
630.000 |
30.1169111100, 78.6213888900 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
39.200 - 39.260
|
60.000 |
30.1120611100, 78.6185111100 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
39.260 - 39.900
|
640.000 |
30.1118750000, 78.6181694400 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
39.900 - 39.970
|
70.000 |
30.1111388900, 78.6136027800 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
39.970 - 40.400
|
430.000 |
30.1115333300, 78.6134861100 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
40.400 - 40.450
|
50.000 |
30.1137361100, 78.6110111100 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
40.450 - 40.800
|
350.000 |
30.1140527800, 78.6106361100 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
40.800 - 40.834
|
34.000 |
30.1152638900, 78.6074083300 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
40.835 - 40.903
|
68.000 |
30.1152972200, 78.6074361100 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
40.905 - 40.925
|
20.000 |
30.1153722200, 78.6068777800 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
40.925 - 41.609
|
684.000 |
30.1159166700, 78.6069083300 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
41.610 - 41.660
|
50.000 |
30.1165888900, 78.6016805600 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
41.660 - 42.110
|
450.000 |
30.1170555600, 78.6014638900 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
42.110 - 42.142
|
32.000 |
30.1181388900, 78.5984833300 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
42.145 - 42.313
|
168.000 |
30.1180638900, 78.5981833300 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
42.315 - 42.375
|
60.000 |
30.1176472200, 78.5968944400 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
42.375 - 43.105
|
730.000 |
30.1176222200, 78.5963805600 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
43.105 - 43.205
|
100.000 |
30.1177166700, 78.5918750000 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
43.325 - 43.365
|
40.000 |
30.1189611100, 78.5906416700 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
43.365 - 43.415
|
50.000 |
30.1192361100, 78.5902055600 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
43.415 - 43.440
|
25.000 |
30.1198722200, 78.5898444400 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
43.440 - 43.575
|
135.000 |
30.1199555600, 78.5898472200 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
43.575 - 43.635
|
60.000 |
30.1211277800, 78.5894305600 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
43.635 - 43.675
|
40.000 |
30.1215194400, 78.5897805600 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
43.675 - 43.755
|
80.000 |
30.1215916700, 78.5901138900 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
43.755 - 43.930
|
175.000 |
30.1215138900, 78.5909416700 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
43.930 - 43.980
|
50.000 |
30.1216638900, 78.5920555600 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
43.980 - 44.060
|
80.000 |
30.1219638900, 78.5933500000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
44.060 - 44.278
|
218.000 |
30.1221916700, 78.5940555600 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
44.280 - 44.390
|
110.000 |
30.1226861100, 78.5963555600 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
44.390 - 44.590
|
200.000 |
30.1229388900, 78.5972611100 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
44.590 - 44.990
|
400.000 |
30.1236638900, 78.5991416700 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
45.490 - 45.540
|
50.000 |
30.1295277800, 78.6012388900 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
45.540 - 45.990
|
450.000 |
30.1298638900, 78.6012444400 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
45.990 - 46.040
|
50.000 |
30.1313694400, 78.5975305600 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
46.040 - 46.340
|
300.000 |
30.1317000000, 78.5973333300 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
46.340 - 46.420
|
80.000 |
30.1329055600, 78.5965611100 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
46.420 - 46.596
|
176.000 |
30.1335722200, 78.5968388900 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
46.600 - 46.670
|
70.000 |
30.1349861100, 78.5972000000 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
46.670 - 46.900
|
230.000 |
30.1356361100, 78.5973777800 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
46.900 - 46.976
|
76.000 |
30.1374500000, 78.5978138900 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
46.980 - 47.590
|
610.000 |
30.1380472200, 78.5979388900 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
47.660 - 48.110
|
450.000 |
30.1407000000, 78.5958277800 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
48.110 - 48.175
|
65.000 |
30.1408611100, 78.5954944400 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
48.175 - 48.210
|
35.000 |
30.1414638900, 78.5955027800 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
48.210 - 48.310
|
100.000 |
30.1419416700, 78.5956916700 |
Estimation Done |
0 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
48.310 - 48.435
|
125.000 |
30.1425777800, 78.5954944400 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[76]
Pauri Devpryag Gaja Jajal state highway
|
Crash barrier |
48.680 - 48.950
|
270.000 |
30.1433944400, 78.5955527800 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
0.000 - 0.600
|
600.000 |
30.0733140000, 78.7179190000 |
Identified |
10 |
|
|
|
estimate to be sent |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
0.600 - 0.696
|
96.000 |
30.0732920000, 78.7117870000 |
Estimation Done |
0 |
|
|
|
in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
0.700 - 1.000
|
300.000 |
30.0728410000, 78.7110440000 |
Identified |
10 |
|
|
|
estimate to be sent |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
1.000 - 1.100
|
100.000 |
30.0732370000, 78.7100210000 |
Identified |
10 |
|
|
|
estimate to be sent |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
1.100 - 1.148
|
48.000 |
30.0728660000, 78.7090010000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
1.150 - 1.250
|
100.000 |
30.0726040000, 78.7087660000 |
Identified |
10 |
|
|
|
estimate to be sent |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
1.250 - 1.326
|
76.000 |
30.0727380000, 78.7080520000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
1.330 - 1.780
|
450.000 |
30.0730760000, 78.7078600000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
1.780 - 1.818
|
38.000 |
30.0731520000, 78.7044240000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
1.820 - 1.940
|
120.000 |
30.0732230000, 78.7040310000 |
Identified |
0 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
1.940 - 2.016
|
76.000 |
30.0735280000, 78.7034390000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
2.020 - 2.060
|
40.000 |
30.0735560000, 78.7024280000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
2.100 - 2.200
|
100.000 |
30.0734740000, 78.7021940000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
2.200 - 2.240
|
40.000 |
30.0731720000, 78.7014140000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
2.240 - 2.400
|
160.000 |
30.0729950000, 78.7011740000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
2.400 - 2.492
|
92.000 |
30.0727150000, 78.6993960000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
2.500 - 2.800
|
300.000 |
30.0727950000, 78.6986790000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
2.800 - 2.864
|
64.000 |
30.0718720000, 78.6968280000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
2.900 - 3.300
|
400.000 |
30.0720880000, 78.6964200000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
3.300 - 3.362
|
62.000 |
30.0732260000, 78.6928570000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
3.362 - 3.452
|
90.000 |
30.0735060000, 78.6927970000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
3.452 - 3.504
|
52.000 |
30.0737730000, 78.6920680000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
3.510 - 3.960
|
450.000 |
30.0740760000, 78.6921620000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
3.960 - 4.012
|
52.000 |
30.0758650000, 78.6891050000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
4.015 - 4.365
|
350.000 |
30.0760880000, 78.6889280000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
4.365 - 4.421
|
56.000 |
30.0771370000, 78.6868020000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
4.425 - 4.525
|
100.000 |
30.0767700000, 78.6867590000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
4.525 - 4.581
|
56.000 |
30.0758710000, 78.6867370000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
4.581 - 4.731
|
150.000 |
30.0755790000, 78.6863900000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
4.731 - 4.781
|
50.000 |
30.0741150000, 78.6857020000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
4.781 - 4.837
|
56.000 |
30.0744420000, 78.6859300000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
4.840 - 4.948
|
108.000 |
30.0737670000, 78.6857020000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
4.950 - 5.150
|
200.000 |
30.0729540000, 78.6852210000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
5.150 - 5.250
|
100.000 |
30.0716130000, 78.6840960000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
5.250 - 5.950
|
700.000 |
30.0708920000, 78.6838460000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
5.949 - 6.057
|
108.000 |
30.0665580000, 78.6814400000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
6.060 - 6.410
|
350.000 |
30.0656550000, 78.6808710000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
6.400
|
0.000 |
30.0629680000, 78.6806020000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
6.410 - 6.466
|
56.000 |
30.0633090000, 78.6808710000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
6.470 - 6.570
|
100.000 |
30.0629680000, 78.6806020000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
6.570 - 6.678
|
108.000 |
30.0620390000, 78.6790330000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
6.680 - 7.330
|
650.000 |
30.0613980000, 78.6783770000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
7.330 - 7.442
|
112.000 |
30.0596820000, 78.6724250000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
7.450 - 7.650
|
200.000 |
30.0596730000, 78.6719080000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
7.650 - 7.706
|
56.000 |
30.0588190000, 78.6706030000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
7.710 - 7.760
|
50.000 |
30.0586280000, 78.6701350000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
7.760 - 7.808
|
48.000 |
30.0586220000, 78.6699050000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
7.810 - 7.960
|
150.000 |
30.0588610000, 78.6695410000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
7.960 - 8.004
|
44.000 |
30.0577750000, 78.6686160000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
8.005 - 8.105
|
100.000 |
30.0580720000, 78.6687630000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
8.105 - 8.165
|
60.000 |
30.0585160000, 78.6696170000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
8.165 - 8.565
|
400.000 |
30.0583361100, 78.6697944400 |
Identified |
0 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
8.565 - 8.681
|
116.000 |
30.0578730000, 78.6737480000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
8.685 - 8.935
|
250.000 |
30.0575080000, 78.6745310000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
8.935 - 8.983
|
48.000 |
30.0568310000, 78.6765620000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
8.985 - 9.037
|
52.000 |
30.0569050000, 78.6777490000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
9.040 - 9.390
|
350.000 |
30.0566830000, 78.6773200000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
9.390 - 9.486
|
96.000 |
30.0571920000, 78.6750560000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
9.490 - 9.680
|
190.000 |
30.0569460000, 78.6742100000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
9.680 - 9.792
|
112.000 |
30.0575320000, 78.6726390000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
9.795 - 10.045
|
250.000 |
30.0568810000, 78.6718960000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
10.045 - 10.093
|
48.000 |
30.0557840000, 78.6703080000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
10.100 - 10.600
|
500.000 |
30.0558250000, 78.6695390000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
10.600 - 11.000
|
400.000 |
30.0550970000, 78.6654160000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[468]
Adwani Nahsain Surpur Bahedakhal Khanda motor road
|
Crash barrier |
11.000 - 11.192
|
192.000 |
30.0566530000, 78.6618880000 |
Estimation Done |
0 |
|
|
|
installed in road safety work 2023-24 |
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
0.000 - 0.200
|
200.000 |
30.0729740000, 78.7130310000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
0.200 - 0.400
|
200.000 |
30.0740280000, 78.6515080000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
0.400 - 0.600
|
200.000 |
30.0753950000, 78.6508190000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
0.600 - 0.800
|
200.000 |
30.0770620000, 78.6515950000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
0.800 - 1.000
|
200.000 |
30.0783920000, 78.6513660000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
1.000 - 1.200
|
200.000 |
30.0796560000, 78.6502140000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
1.200 - 1.400
|
200.000 |
30.0802270000, 78.6484830000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
1.400 - 1.600
|
200.000 |
30.0810300000, 78.6468780000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
1.600 - 1.800
|
200.000 |
30.0815150000, 78.6451330000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
1.800 - 2.000
|
200.000 |
30.0808970000, 78.6435790000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
2.000 - 2.200
|
200.000 |
30.0823800000, 78.6424080000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
2.200 - 2.400
|
200.000 |
30.8369600000, 78.6418410000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
2.400 - 2.600
|
200.000 |
30.0842000000, 78.6401830000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
2.600 - 2.800
|
200.000 |
30.0842090000, 78.6401600000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
2.800 - 3.000
|
200.000 |
30.0836330000, 78.6364640000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
3.000 - 3.200
|
200.000 |
30.0845570000, 78.6350950000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
3.200 - 3.400
|
200.000 |
30.0855640000, 78.6336990000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
3.400 - 3.600
|
200.000 |
30.0851470000, 78.6316640000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
3.600 - 3.800
|
200.000 |
30.0848840000, 78.6297960000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
3.800 - 4.000
|
200.000 |
30.0851710000, 78.6282190000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
4.000 - 4.200
|
200.000 |
30.0854020000, 78.6265660000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
4.200 - 4.400
|
200.000 |
30.0860240000, 78.6249040000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
4.400 - 4.550
|
150.000 |
30.0857450000, 78.6230220000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
4.570 - 4.600
|
30.000 |
30.0863510000, 78.6230420000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
4.600 - 4.800
|
200.000 |
30.0869780000, 78.6234220000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
4.800 - 4.860
|
60.000 |
30.0882340000, 78.6223760000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3509]
Surpur Lasera Danda Nagraja Ghindwada motor road
|
Crash barrier |
4.980 - 5.000
|
20.000 |
30.0883120000, 78.6213380000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3647]
Ufalda Khandukhal Muchiyali Charakot Jamlakhal Ghurdodi motor road
|
Crash barrier |
29.300 - 29.387
|
87.000 |
30.1838160000, 78.6795280000 |
Estimation Done |
0 |
|
|
|
in sas work 2022-23 |
Jul 2025 |
[3647]
Ufalda Khandukhal Muchiyali Charakot Jamlakhal Ghurdodi motor road
|
Crash barrier |
29.400 - 29.508
|
108.000 |
30.1828670000, 78.6795500000 |
Estimation Done |
0 |
|
|
|
in sas work 2022-23 |
Jul 2025 |
[3647]
Ufalda Khandukhal Muchiyali Charakot Jamlakhal Ghurdodi motor road
|
Crash barrier |
29.500 - 29.700
|
200.000 |
30.1826666700, 78.6797027800 |
Identified |
10 |
|
|
|
estimate to be sent |
Jul 2025 |
[3647]
Ufalda Khandukhal Muchiyali Charakot Jamlakhal Ghurdodi motor road
|
Crash barrier |
29.700 - 29.900
|
200.000 |
30.1829300000, 78.6807520000 |
Identified |
10 |
|
|
|
estimate to be sent for approval |
Jul 2025 |
[3647]
Ufalda Khandukhal Muchiyali Charakot Jamlakhal Ghurdodi motor road
|
Crash barrier |
29.900 - 29.936
|
36.000 |
30.1829300000, 78.6807520000 |
Estimation Done |
0 |
|
|
|
in sas work 2022-23 |
Jul 2025 |
[3647]
Ufalda Khandukhal Muchiyali Charakot Jamlakhal Ghurdodi motor road
|
Crash barrier |
30.000 - 30.200
|
200.000 |
30.1836890000, 78.6853230000 |
Identified |
10 |
|
|
|
estimate to be sent |
Jul 2025 |
[3647]
Ufalda Khandukhal Muchiyali Charakot Jamlakhal Ghurdodi motor road
|
Crash barrier |
30.200 - 30.400
|
200.000 |
30.1841450000, 78.6874140000 |
Identified |
10 |
|
|
|
estimate to be sent |
Jul 2025 |
[3647]
Ufalda Khandukhal Muchiyali Charakot Jamlakhal Ghurdodi motor road
|
Crash barrier |
30.400 - 30.600
|
200.000 |
30.1839670000, 78.6882330000 |
Identified |
10 |
|
|
|
estimate to be sent |
Jul 2025 |
[3647]
Ufalda Khandukhal Muchiyali Charakot Jamlakhal Ghurdodi motor road
|
Crash barrier |
30.600 - 30.676
|
76.000 |
30.1839670000, 78.6881330000 |
Estimation Done |
0 |
|
|
|
in sas work 2022-23 |
Jul 2025 |
[3647]
Ufalda Khandukhal Muchiyali Charakot Jamlakhal Ghurdodi motor road
|
Crash barrier |
30.680 - 30.880
|
200.000 |
30.1835640000, 78.6900210000 |
Identified |
10 |
|
|
|
estimate to be sent |
Jul 2025 |
[3647]
Ufalda Khandukhal Muchiyali Charakot Jamlakhal Ghurdodi motor road
|
Crash barrier |
30.880 - 31.080
|
200.000 |
30.1831430000, 78.6907600000 |
Identified |
0 |
|
|
|
estimate to be sent |
Jul 2025 |
[3647]
Ufalda Khandukhal Muchiyali Charakot Jamlakhal Ghurdodi motor road
|
Crash barrier |
31.080 - 31.152
|
72.000 |
30.1825990000, 78.6920440000 |
Estimation Done |
10 |
|
|
|
in sas work 2022-23 |
Jul 2025 |
[3647]
Ufalda Khandukhal Muchiyali Charakot Jamlakhal Ghurdodi motor road
|
Crash barrier |
31.200 - 31.344
|
144.000 |
30.1810660000, 78.6933140000 |
Estimation Done |
0 |
|
|
|
in sas work 2022-23 |
Jul 2025 |
[3647]
Ufalda Khandukhal Muchiyali Charakot Jamlakhal Ghurdodi motor road
|
Crash barrier |
31.400 - 31.412
|
12.000 |
30.1809900000, 78.6946720000 |
Estimation Done |
0 |
|
|
|
in sas work 2022-23 |
Jul 2025 |
[3647]
Ufalda Khandukhal Muchiyali Charakot Jamlakhal Ghurdodi motor road
|
Crash barrier |
31.420 - 31.595
|
175.000 |
30.1798900000, 78.6945660000 |
Identified |
10 |
|
|
|
estimate to be sent |
Jul 2025 |
[3647]
Ufalda Khandukhal Muchiyali Charakot Jamlakhal Ghurdodi motor road
|
Crash barrier |
31.600 - 31.800
|
200.000 |
30.1794140000, 78.6988790000 |
Identified |
10 |
|
|
|
estimate to be sent |
Jul 2025 |
[3647]
Ufalda Khandukhal Muchiyali Charakot Jamlakhal Ghurdodi motor road
|
Crash barrier |
31.800 - 31.850
|
50.000 |
30.1794560000, 78.6942510000 |
Estimation Done |
0 |
|
|
|
in sas work 2022-23 |
Jul 2025 |
[3647]
Ufalda Khandukhal Muchiyali Charakot Jamlakhal Ghurdodi motor road
|
Crash barrier |
31.850 - 31.950
|
100.000 |
30.1792810000, 78.6991630000 |
Identified |
10 |
|
|
|
estimate to be sent |
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
0.000 - 0.100
|
100.000 |
30.1567190000, 78.7689160000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
0.100 - 0.200
|
100.000 |
30.1567200000, 78.7689120000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
0.200 - 0.300
|
100.000 |
30.1567210000, 78.7689210000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
0.300 - 0.332
|
32.000 |
30.1577580000, 78.7684070000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
0.332 - 0.372
|
40.000 |
30.1580620000, 78.7675250000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
0.372 - 0.412
|
40.000 |
30.1580330000, 78.7678750000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
0.412 - 0.512
|
100.000 |
30.1578630000, 78.7684170000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
0.512 - 0.624
|
112.000 |
30.1581110000, 78.7694670000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
0.624 - 0.778
|
154.000 |
30.1582360000, 78.7680350000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
0.778 - 0.854
|
76.000 |
30.1582790000, 78.7670840000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
0.854 - 1.004
|
150.000 |
30.1592740000, 78.7622400000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
1.004 - 1.054
|
50.000 |
30.1589050000, 78.7662960000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
1.054 - 1.254
|
200.000 |
30.1590120000, 78.7663970000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
1.254 - 1.504
|
250.000 |
30.1617420000, 78.7659960000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
1.504 - 1.654
|
150.000 |
30.1623400000, 78.7653910000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
1.654 - 1.804
|
150.000 |
30.1643060000, 78.7653070000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
1.804 - 1.968
|
164.000 |
30.1651170000, 78.7665900000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
1.968 - 2.118
|
150.000 |
30.1653280000, 78.7675960000 |
Identified |
8 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
2.118 - 2.232
|
114.000 |
30.1662810000, 78.7682330000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
2.232 - 2.432
|
200.000 |
30.1672790000, 78.7681540000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
2.432 - 2.496
|
64.000 |
30.1669400000, 78.7676720000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
2.496 - 2.646
|
150.000 |
30.1666430000, 78.7656720000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
2.646 - 2.746
|
100.000 |
30.1669980000, 78.7650170000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
2.746 - 2.946
|
200.000 |
30.1671240000, 78.7643010000 |
Identified |
100 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
2.946 - 3.146
|
200.000 |
30.1669890000, 78.7635090000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
3.146 - 3.446
|
300.000 |
30.1674610000, 78.7604720000 |
Identified |
100 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
3.446 - 3.656
|
210.000 |
30.1672350000, 78.7589430000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
3.656 - 3.766
|
110.000 |
30.1672360000, 78.7589150000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
3.766 - 3.816
|
50.000 |
30.1672690000, 78.7577730000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
3.816 - 3.916
|
100.000 |
30.1686600000, 78.7572440000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
3.916 - 4.040
|
124.000 |
30.1690910000, 78.7571220000 |
Estimation Done |
1 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
4.040 - 4.220
|
180.000 |
30.1694090000, 78.7557830000 |
Estimation Done |
1 |
|
|
|
no need of crash barrier bcz of parapet installed |
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
4.220 - 5.820
|
1600.000 |
30.1790100000, 78.7479720000 |
Identified |
10 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
5.820 - 5.870
|
50.000 |
30.1797100000, 78.7480980000 |
Identified |
9 |
|
|
|
|
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
5.870 - 5.950
|
80.000 |
30.1799860000, 78.7481940000 |
Estimation Done |
1 |
|
|
|
Residential area , So no need of crash barrier |
Jul 2025 |
[3649]
Pauri Dehlchauri Uflada motor road
|
Crash barrier |
5.950 - 6.000
|
50.000 |
30.1803850000, 78.7485250000 |
Identified |
9 |
|
|
|
|
Jul 2025 |
[94]
Tehri Hindolakhal Devprayag Vyasghat Bilkhet state highway
|
Informatory board |
57.000
|
0.000 |
30.1453750000, 78.6044320000 |
Estimation Done |
0 |
|
|
|
|
May 2025 |
[3640]
Rashi Kyunkaleshwar road
|
Slide Zone |
0.300 - 0.360
|
60.000 |
30.1533333300, 78.7616667000 |
Identified |
10 |
|
|
|
Road open for light vehicles. |
Jan 2024 |